Can you build a CPM/PERT network noting the activity numbers and duration based on the activity table below?
Can you build a CPM/PERT network noting the activity numbers and duration based on the activity table below? Can you identify the critical path through the network, determine the project completion time, and determine the earliest and latest start dates for each node? Activity Predecessor Time(days) 1 – 2 2 – 8 3 1 3 4 1,2 6 5 3 3 6 3 5 7 4,5,6 10
. .
The post Can you build a CPM/PERT network noting the activity numbers and duration based on the activity table below? appeared first on USA Dissertation Editors.